Bendpro/CAA for Georgiou

    Date – November 13, 2019
    Source of issue –Bendpro Supplied only 50% of Clamp order.
    Description –

    21MAY19: LS requested quote for 366 pipe clamps according to the our customer drawing drg N2253-1_MA_ST_1212.
    03JUN19: LS also emailed marked up CAA drawings showing dimensions and quantities for complete clamp assemblies (not halves), backed up by email wording.
    George from Bendpro misinterpreted these requirements.

    13NOV19: Working on solution.


    Immediate action –Bendpro are fabricating the other 50% so that we meet delivery deadline.
    Root cause –Bendpro insufficient attention to detail in RFQ and subsequent documentation.
    Corrective action –

    13NOV19: Resolution yet to be determined.
    02NOV20: CAA and Bendpro agreed to supply the correct no. of clamps at cost (no profit) to ensure customer happy. It was put down to a misinterpretation of wording and drawings.

    Verification –
    Reported by –BL
    Closed by –BL
    Date closed –November 2, 2020